Cherry Street Reconstruction
Project P-PH-EM
2050 (06) 408
SD Highways 50 & 50L
Vermillion, Clay County

                                           Paving Sequence

Date:  August 18, 2008 

To:  Property Owners 

From:  Greg Branaugh 

Ref:  Cherry Street Paving Sequence
         Pending Weather Difficulties

Please be advised of the following concrete paving sequence and subsequent driveway closures on the Cherry Street project from Jefferson St. to 500’ east of Crawford Road on the South Side:

Week of: Aug. 18 – 22    Curb, Gutter & Paving Cherry St. Plaza to Jefferson St.

Week of: Aug. 25 – 29    Curb, Gutter, Paving Jefferson St. to Norbeck St.,
                             Curb & Gutter Norbeck St. to West side of 1441 Cherry St.

Week of: Sept. 2 – 6        Curb, Gutter, Paving West of 1441 Cherry St. to East end  of Project through Crawford Road 

When the Curb & Gutter stringline is set up expect a 7-10 day closure of driveways.  We will blanket the driveway at 1433 Cherry St. to allow access prior to closing 1441.  Please coordinate your parking during these closures.

Your cooperation during these inconveniences is appreciated.  We will attempt to make these project sequences as convenient as possible.