Cherry Street
Reconstruction
Project P-PH-EM
2050 (06) 408
SD Highways 50 & 50L
Vermillion, Clay County
|
Paving Sequence Date: August 18, 2008 To: Property Owners From: Greg Branaugh Ref: Cherry
Street Paving Sequence Please be advised of the following concrete paving sequence and subsequent driveway closures on the Cherry Street project from Jefferson St. to 500’ east of Crawford Road on the South Side: Week of: Aug. 18 – 22 Curb, Gutter & Paving Cherry St. Plaza to Jefferson St.
Week of: Aug. 25 – 29 Curb,
Gutter, Paving Jefferson St. to Norbeck St., Week of: Sept. 2 – 6 Curb, Gutter, Paving West of 1441 Cherry St. to East end of Project through Crawford Road When the Curb & Gutter stringline is set up expect a 7-10 day closure of driveways. We will blanket the driveway at 1433 Cherry St. to allow access prior to closing 1441. Please coordinate your parking during these closures. Your cooperation during these inconveniences is appreciated. We will attempt to make these project sequences as convenient as possible. Thank you.
|